Labs/Site 2.0/Roadmap + schedule
From MozillaWiki
- DONE Initial mockups/wireframes complete: Apr 10 (Sean/Neil)
- DONE Project mockup content: Apr 10 (Deb)
- DONE Initial testplan (SDonner)
- DONE Feedback from stakeholders/community complete: Apr 27 (allhands - Labs team)
- DONE Final mockups/wireframes complete:
Apr 24May 8 (Sean/Neil) - DONE WPMU infrastructure setup Apr 24 (Ryan/IT)
- Full content list + copy ready:
Jun 1Jun 15 (Deb) - WPMU templates complete:
Jun 12Jul 3 (8 weeks - Ryan/Neil) - WPMU plugins: Jul 3 (Ryan/IT)
- Content into site:
Jun 21Jul 10 (3 wks - Deb/Labs) - Launch planning:
Jun 19Jul 18 (5 days - Deb/Beard)
- QA/Testing (ongoing, as soon as there's something to test)
- Launch: TBD (Deb/Beard)
MISSED! "Before the end of June" is the ideal launch target.
Let's try for "Before the end of July" now.