Summary
DOC VERSION: 1.0 STATUS REPORT AS OF: July 30, 2012
AUTHOR: Benjamin Sternthal
TPM: Benjamin Sternthal
PROJECT SPONSOR: Pierros Papadeas
PROJECT WIKI: Websites/ReMo_Mozilla_Reps
Status
1. STATUS
Status Item On Track Caution Crisis N/A Comment
OVERALL STATUS X
Schedule X
Scope X
Budget X
Schedule & Budget
2. SCHEDULE
Start Date Completion Date
Original Current Original Current
May 30 2012 May 30 2012 R 0.3 July 23 2012 R 0.3 July 31 2012
Recent Accomplishments
4. RECENT ACCOMPLISHMENTS
  • QA continues
  • Infra Sec Review Complete
Upcoming Tasks
5. UPCOMING TASKS
Task Owner Due Date Bugzilla Comments
Plan For In-Complete Affiliates API PP - - Complete
Bedrock: Contribute Tracking PP - 764893 Complete
Major Issues
6. MAJOR ISSUES, CONCERNS & IMPACTS (* = new)
Issue Description Owner Priority Date Due Bugzilla Status
- - - - - -
Project Milestones
7. PROJECT MILESTONES & SCHEDULE
Smartsheet Schedule