Websites/ReMo Mozilla Reps/Weekly-Status-Reports/2012-05-14

From MozillaWiki
Jump to: navigation, search
Summary
DOC VERSION: 1.0 STATUS REPORT AS OF: May 14, 2012
AUTHOR: Benjamin Sternthal
TPM: Benjamin Sternthal
PROJECT SPONSOR: Pierros Papadeas
PROJECT WIKI: Websites/ReMo_Mozilla_Reps
Status
1. STATUS
Status Item On Track Caution Crisis N/A Comment
OVERALL STATUS X
Schedule X
Scope X
Budget X
Schedule & Budget
2. SCHEDULE
Start Date Completion Date
Original Current Original Current
April 9 2012 April 9 2012 R 0.2.5 May 21, 2011 R 0.2.5 May 23, 2011
Recent Accomplishments
4. RECENT ACCOMPLISHMENTS
  • Deploy to stage May 14?
  • 0.2.5 Coding Continues
  • QA Started
Upcoming Tasks
5. UPCOMING TASKS
Task Owner Due Date Bugzilla Comments
- - - - -
Major Issues
6. MAJOR ISSUES, CONCERNS & IMPACTS (* = new)
Issue Description Owner Priority Date Due Bugzilla Status
- - - - - -
Project Milestones
7. PROJECT MILESTONES
Issue Owner Target
Completion
Date
Revised
Completion
Date
Actual
Completion
Date
Bugzilla Status
ReMo Team
  Release 0.2.5 Ready To Test GL 5/14 5/16
  Release 0.2.5 Live GL 5/21 5/23
Privacy/Legal
  Release 0.2.5 Review SM 5/7 - 5/11 743853 N/A
QA
  Release 0.2.5 Review RB 5/10 - 5/18 745313
Security
  Release 0.2.5 Review YB 5/14 - 5/16 745314
Design
  Design Review JS 4/20 Complete