DOC VERSION: 1.0 STATUS REPORT AS OF: April 02, 2012
AUTHOR: Benjamin Sternthal
TPM: Benjamin Sternthal
PROJECT SPONSOR: Pierros Papadeas
PROJECT WIKI: Websites/ReMo_Mozilla_Reps
Status
1. STATUS
Status Item On Track Caution Crisis N/A Comment
OVERALL STATUS X
Schedule X
Scope X
Budget X
Schedule & Budget
2. SCHEDULE
Start Date Completion Date
Original Current Original Current
Jan 30 2012 Jan 30 2012 R2 April 2, 2011 April 4
Recent Accomplishments
4. RECENT ACCOMPLISHMENTS
  • R2 Coding Complete
  • Coding Bugfixes & Feedback
  • Test Day Complete
Upcoming Tasks
5. UPCOMING TASKS
Task Owner Due Date Bugzilla Comments
Co-ordinate Design Review BS 2012-03-14 - Complete
Major Issues
6. MAJOR ISSUES, CONCERNS & IMPACTS (* = new)
Issue Description Owner Priority Date Due Bugzilla Status
- - - - - -
Project Milestones
7. PROJECT MILESTONES
Issue Owner Target
Completion
Date
Revised
Completion
Date
Acutal
Completion
Date
Bugzilla Status
ReMo Team
  Release 2 Ready To Test GL 3/16 - 3/23 3/28
  Release 2 Live GL 4/2
  Release 3 Live GL --
WebDev
  Release 2 Review JW & PM 3/19 - 3/21 In Progress
Privacy/Legal
  Release 2 Review SM 3/19 - 3/28 733027 In Progress
QA
  Release 2 Review SD 3/15 - 3/26 732223 In Progress
Security
  Release 2 Review YB 3/26 - 3/30 733020 In Progress
Design
  Design Review JS 4/5 - 4/9