Websites/ReMo Mozilla Reps/Weekly-Status-Reports/2012-03-05
From MozillaWiki
Contents
Summary
DOC VERSION: 1.0 | STATUS REPORT AS OF: March 05, 2012 |
AUTHOR: Benjamin Sternthal |
TPM: Benjamin Sternthal |
PROJECT SPONSOR: Pierros Papadeas |
PROJECT WIKI: Websites/ReMo_Mozilla_Reps |
Status
1. STATUS | |||||
Status Item | On Track | Caution | Crisis | N/A | Comment |
OVERALL STATUS | X | ||||
Schedule | X | ||||
Scope | X | ||||
Budget | X |
Schedule & Budget
2. SCHEDULE | |||
Start Date | Completion Date | ||
Original | Current | Original | Current |
Jan 30 2012 | Jan 30 2012 | April 11, 2011 | N/A |
3. BUDGET | |||
Original | Current Cost Of Work Performed |
Estimated Actual Cost |
Variance at Completion |
N/A | N/A | N/A | N/A |
Recent Accomplishments
4. RECENT ACCOMPLISHMENTS |
|
Upcoming Tasks
5. UPCOMING TASKS | ||||
Task | Owner | Due Date | Bugzilla | Comments |
Launch Release 1 | Pierros | 2012-02-28 | - | Complete |
Approve Milestone Dates Of Release 2 | Teams | 2012-03-02 | - | In Progress |
Scope & Plan + Milestone Dates Of Release 2 | Pierros/BS | 2012-02-20 | - | Complete |
Major Issues
6. MAJOR ISSUES, CONCERNS & IMPACTS (* = new) | |||||||
Issue Description | Owner | Priority | Date Due | Bugzilla | Status | ||
- | - | - | - | - | - |
Project Milestones
7. PROJECT MILESTONES | |||||||
Issue | Owner | Target Completion Date |
Revised Completion Date |
Acutal Completion Date |
Bugzilla | Status | |
ReMo Team | |||||||
Release 1 Ready To Test | GL | 2/3 | 2/7 | 2/9 | Complete | ||
Release 1 Live | GL | 2/28 | 2/28 | Complete | |||
Release 2 Ready To Test | GL | 3/16 | |||||
Release 2 Live | GL | 4/2 | |||||
Release 3 Live | GL | -- | |||||
WebDev | |||||||
Release 1 Review | JW & PM | 2/3 - 2/6 | 2/9 - 2/10 | 2/10 | Complete | ||
Release 2 Review | JW & PM | 3/19 - 3/21 | |||||
Privacy/Legal | |||||||
Release 1 Review | SM | 2/8 - 2/24 | 722528 | Complete | |||
Release 2 Review | SM | 3/19 - 3/28 | 733027 | ||||
QA | |||||||
Release 1 Review | SD | 2/8 - 2/15 | 722518 | Complete | |||
Release 2 Review | SD | 3/15 - 3/26 | 732223 | ||||
Security | |||||||
Release 1 Review | YB | 2/15 - 2/24 | 722521 | Complete | |||
Release 2 Review | YB | 3/26 - 3/30 | 733020 | ||||
IT | |||||||
Setup Dev | JM | 1/30 | 718584 | Complete | |||
Setup Staging | JM | 2/14 | 2/13 | 719262 | Complete | ||
Setup Production | JM | 2/24 | 2/9 | 720473 | Complete |