Summary
DOC VERSION: 1.0 STATUS REPORT AS OF: Feb 20, 2012
AUTHOR: Benjamin Sternthal
TPM: Benjamin Sternthal
PROJECT SPONSOR: Pierros Papadeas
PROJECT WIKI: Websites/ReMo_Mozilla_Reps
Status
1. STATUS
Status Item On Track Caution Crisis N/A Comment
OVERALL STATUS X
Schedule X
Scope X
Budget X
Schedule & Budget
2. SCHEDULE
Start Date Completion Date
Original Current Original Current
Jan 30 2012 Jan 30 2012 April 11, 2011 N/A
3. BUDGET
Original Current
Cost Of Work
Performed
Estimated
Actual Cost
Variance
at
Completion
N/A N/A N/A N/A
Recent Accomplishments
4. RECENT ACCOMPLISHMENTS
  • Met with Comm Tools/Platforms, yep there is some overlap, nope we can't use any of there stuff yet... but soon!
  • Planning Release 2
  • Testing / Bugfixing continuing
Upcoming Tasks
5. UPCOMING TASKS
Task Owner Due Date Bugzilla Comments
Scope & Plan + Milestone Dates Of Release 2 Pierros/BS 2012-02-20 - In progress
Approve Milestone Dates Of Release 2 Teams 2012-02-23 - Not Started
Major Issues
6. MAJOR ISSUES, CONCERNS & IMPACTS (* = new)
Issue Description Owner Priority Date Due Bugzilla Status
- - - - - -
Project Milestones
7. PROJECT MILESTONES
Issue Owner Target
Completion
Date
Revised
Completion
Date
Acutal
Completion
Date
Bugzilla Status
ReMo Team
  Release 1 Ready To Test GL 2/3 2/7 2/9 Complete
  Release 1 Live GL 2/28
  Release 2 Ready To Test GL 3/5 (Tent)
  Release 2 Live GL 3/19 (Tent)
  Release 3 Live GL TBD
WebDev
  Release 1 Review JW & PM 2/3 - 2/6 2/9 - 2/10 2/10 Complete
  Release 2 Review JW & PM 3/5 - 3/7
Privacy/Legal
  Release 1 Review SM 2/8 - 2/24 722528
  Release 2 Review N/A (Confirm)
QA
  Release 1 Review SD 2/8 - 2/15 722518 In Progress
  Release 2 Review SD 3/5 - 3/12
Security
  Release 1 Review YB 2/15 - 2/24 722521
  Release 2 Review YB 3/12 - 3/16
IT
  Setup Dev JM 1/30 718584 Complete
  Setup Staging JM 2/14 2/13 719262 Complete
  Setup Production JM 2/24 2/9 720473 Complete