Websites/ReMo Mozilla Reps/Weekly-Status-Reports/2012-02-06

From MozillaWiki
Jump to: navigation, search
Summary
DOC VERSION: 1.0 STATUS REPORT AS OF: Feb 6, 2012
AUTHOR: Benjamin Sternthal
TPM: Benjamin Sternthal
PROJECT SPONSOR: Pierros Papadeas
PROJECT WIKI: Websites/ReMo_Mozilla_Reps
Status
1. STATUS
Status Item On Track Caution Crisis N/A Comment
OVERALL STATUS X
Schedule X
Scope X
Budget X
Schedule & Budget
2. SCHEDULE
Start Date Completion Date
Original Current Original Current
Jan 30 2012 Jan 30 2012 April 11, 2011 N/A
3. BUDGET
Original Current
Cost Of Work
Performed
Estimated
Actual Cost
Variance
at
Completion
N/A N/A N/A N/A
Recent Accomplishments
4. RECENT ACCOMPLISHMENTS
  • Paul & Jenn & Giorgois had meeting, code review workflo defined
  • Milestone schedule sent around... need confirmation on dates
  • Scheduled twice monthly checkin with Aakash
Upcoming Tasks
5. UPCOMING TASKS
Task Owner Due Date Bugzilla Comments
Fill Out Milestone Schedule BS & Teams 02/03/2012 - Need Review
Code Freeze & First Code Review Giorgios/PM/JF 02/07/2012 - -
Plan Scope/Dates Of Release 2 Peirros/BS 02/10/2012 - -
Major Issues
6. MAJOR ISSUES, CONCERNS & IMPACTS (* = new)
Issue Description Owner Priority Date Due Bugzilla Status
- - - - - -
Project Milestones
7. PROJECT MILESTONES
Issue Owner Target
Completion
Date
Revised
Completion
Date
Acutal
Completion
Date
Bugzilla Status
ReMo Team
  Release 1 Ready To Test GL 2/3 2/7
  Release 1 Live GL 2/28
  Release 2 Live GL TBD
  Release 3 Live GL TBD
WebDev
  Release 1 Review JW & PM 2/3 - 2/6 2/7 - 2/8
  
Privacy/Legal
  Release 1 Review SM 2/8 - 2/24 722528
  
QA
  Release 1 Review SD 2/8 - 2/15 722518
  
Security
  Release 1 Review YB 2/15 - 2/24 722521
  
IT
  Setup Dev JM 1/30 718584 Complete
  Setup Staging JM 2/14 719262 In Progress
  Setup Production JM 2/24 720473 In Progress