Summary
DOC VERSION: 1.0 | STATUS REPORT AS OF: Jan 30, 2012 |
AUTHOR: Benjamin Sternthal |
TPM: Benjamin Sternthal |
PROJECT SPONSOR: Pierros Papadeas |
PROJECT WIKI: Websites/ReMo_Mozilla_Reps |
Status
1. STATUS | |||||
Status Item | On Track | Caution | Crisis | N/A | Comment |
OVERALL STATUS | X | ||||
Budget | X | ||||
Schedule | X | ||||
Scope | X |
Schedule & Budget
2. SCHEDULE | |||
Start Date | Completion Date | ||
Original | Current | Original | Current |
N/A | N/A | N/A | N/A |
3. BUDGET | |||
Original | Current Cost Of Work Performed |
Estimated Actual Cost |
Variance at Completion |
N/A | N/A | N/A | N/A |
Recent Accomplishments
4. RECENT ACCOMPLISHMENTS |
|
Upcoming Tasks
5. UPCOMING TASKS | ||||
Task | Owner | Due Date | Bugzilla | Comments |
Fill Out Milestone Schedule | BS & Teams | 02/03/2012 | - | - |
Schedule WebDev Reviews | BS & Teams | 02/01/2012 | - | - |
Schedule twice monthly checkin with Aakash | BS & PP | 02/01/2012 | - | - |
Figure out & document what will be code reviewed | Paul/Giorgios/BS | 02/03/2012 | - | - |
Major Issues
6. MAJOR ISSUES, CONCERNS & IMPACTS (* = new) | |||||||
Issue Description | Owner | Priority | Date Due | Bugzilla | Status | ||
- | - | - | - | - | - |
Project Milestones
7. PROJECT MILESTONES | |||||||
Issue | Owner | Target Completion Date |
Revised Completion Date |
Acutal Completion Date |
Bugzilla | Status | |
ReMo Team | |||||||
WebDev | |||||||
IT | |||||||
Security | |||||||
Privacy | |||||||