Websites/Mozillians.org/Meetings/June 30th 2011

From MozillaWiki
Jump to: navigation, search

Timelines

See the Timeline and Gantt chart spreadsheet for details.

Notes

  • Andrew done with phase 1 LDAP
  • Web dev offsite last week so no work done
  • tofumatt and ddash on other projects, not full time on mozillians
  • security diagram is done
  • setting up vagrant vm this week to kick tires on prototype
  • back end details more complex than thought
  • need to fork the libraries, ldap, other
  • tofumatt out next week
  • ozten out 2 weeks
  • ddash is around
    • creating a secure session is unanticipated but ddash will work on it.

Contract for ldap

  • phase 1 is 1.0
  • phase 2 training session with ops
  • phase 3 advance privacy features

prototype

  • eod friday vm will be ready to start up local instance of prototype

training session. who?

  • 2 web dev team, 2 ops and a few on laura's team
  • mid August
  • Mike will talk to Corey and Laura mid July

Timeline

  • vacation and others may affect July 30 launch date
  • do we want to get a contractor involved?
  • Get another internal developers?
  • ddash will talk to Caktus about contracting for dev

Time estimate:

  • Front end work is three weeks
  • back end three weeks
  • could get Silver Orange on it
  • or tofumatt full time
  • David will follow up on with SO on there availability

L10n

  • were going to start this weekend
  • don’t need front end to be complete but need strings frozen
  • doesn’t need to look good.
  • Shouldn’t be dependent on other tasks

Security and QA

  • 2 weeks shouldn’t be a problem
  • app should be code complete
  • Security diagram is done and handed off
  • Aakash will follow up with Raymond (infrasec)