Unified Telemetry/Status reports/EventTelemetry/Sept 7 2016
From MozillaWiki
[previous weeks report]
Contents
Event Telemetry status report Sept 7, 2016
Overall Project Health
Last week: Yellow
This week: Yellow
Exec Summary
- Project remains in yellow as we continue to understand dependencies and address architectural issues
- DB vs black box being sketched out via shim
- FF client side work begins next week
- Meetings with AS folks
Risks/Issues
Description of Risks/Issues | State | Owner | Plan to Resolve/Mitigation | Target Date |
---|---|---|---|---|
Get sign off on proposal | In process | Georg | sign offs required from TestPilot (Will Clouser), Ilana, RobFromBRC, John Dorlus, | ASAP |
Notify Org post signoff | TBD | Thomas/Georg | Notify FX-Team, UITour stakholders, Jared, Mike Connoly | TBD |
Assess what event measurements in Activity Stream can be measured via the Event Telemetry approach | done | Ilana | Investigate | done |
Escalate request for UX feedback to Product and Data leadership | In process | Katie | Escalation | In flight |
event registry integration in add-ons | Done | Georg | seek consensus | Done |
Accomplished for Last Period
- Assessed what event measurements in Activity Stream can be measured via the Event Telemetry approach
- process defined for the event registry integration in add-ons (glind, mattg, mark banner)
- reached out, on-board so far: addons team, mbanner, test-pilot
- ongoing discussion around architectural issues DB vs. blackbox
- Ilana recommends reimplement everything that is in AS in event based telemetry
- Event Telemetery - First prototype is AS (no requirement to use data platform pipeline)
Planned for Next Period
- Ilana set up a meeting with Marina/Georg/Ilana
- DB vs. blackbox
- Georg to sketch it out prototype/shim implementation in test pilot and work with will
- Thomas and Katie to work on event / probe dependencies matrix
- Firefox client-side work starting next week
- Georg & Ilana to meet to clear up last detail questions on event draft
- Risk - Still missing a "prototype" project to guide the work from
- KP to email Tim Spurway wrt to AS
Proposed development stages and status
Stage | State | description | Target Date |
---|---|---|---|
Proposal creation | Done | accepted | August 1, 2016 |
Kick off | Done | RACI + develpoment stages | August 14, 2016 |
Development to allow test pilot to begin using and submitting | TBD | ingestion, storage, make available for analysis | TBD |
QA Validation | TBD | Test to validate UITelemtry | TBD |
Processing | TBD | TBD | TBD |
Tooling | TBD | TBD | TBD |
Probe / Event dependancies and timeline
Name of probe | design and review | Use cases / questions | list of events & priorities for implementation | who implements and owns the probe | who owns analysis |
---|---|---|---|---|---|
Activity Stream Events | design | use cases | event list | implement and own | analysis owner |
UItelemetry Events | design | use cases | event list | implement and own | analysis owner |
Search events | design | use cases | event list | implement and own | analysis owner |
Engagement measures events | design | use cases | event list | implement and own | analysis owner |
Test pilot events | design | use cases | event list | implement and own | analysis owner |
Mobile Telemetry | design | use cases | event list | implement and own | analysis owner |