Event Telemetry status report Sept 7, 2016

Overall Project Health

Last week: Yellow

This week: Yellow

Exec Summary

  • Project remains in yellow as we continue to understand dependencies and address architectural issues
    • DB vs black box being sketched out via shim
  • FF client side work begins next week
  • Meetings with AS folks

Risks/Issues

Description of Risks/Issues State Owner Plan to Resolve/Mitigation Target Date
Get sign off on proposal In process Georg sign offs required from TestPilot (Will Clouser), Ilana, RobFromBRC, John Dorlus, ASAP
Notify Org post signoff TBD Thomas/Georg Notify FX-Team, UITour stakholders, Jared, Mike Connoly TBD
Assess what event measurements in Activity Stream can be measured via the Event Telemetry approach done Ilana Investigate done
Escalate request for UX feedback to Product and Data leadership In process Katie Escalation In flight
event registry integration in add-ons Done Georg seek consensus Done

Accomplished for Last Period

  • Assessed what event measurements in Activity Stream can be measured via the Event Telemetry approach
  • process defined for the event registry integration in add-ons (glind, mattg, mark banner)
    • reached out, on-board so far: addons team, mbanner, test-pilot
  • ongoing discussion around architectural issues DB vs. blackbox
  • Ilana recommends reimplement everything that is in AS in event based telemetry
  • Event Telemetery - First prototype is AS (no requirement to use data platform pipeline)

Planned for Next Period

  • Ilana set up a meeting with Marina/Georg/Ilana
  • DB vs. blackbox
    • Georg to sketch it out prototype/shim implementation in test pilot and work with will
  • Thomas and Katie to work on event / probe dependencies matrix
  • Firefox client-side work starting next week
    • Georg & Ilana to meet to clear up last detail questions on event draft
    • Risk - Still missing a "prototype" project to guide the work from
  • KP to email Tim Spurway wrt to AS

Proposed development stages and status

Stage State description Target Date
Proposal creation Done accepted August 1, 2016
Kick off Done RACI + develpoment stages August 14, 2016
Development to allow test pilot to begin using and submitting TBD ingestion, storage, make available for analysis TBD
QA Validation TBD Test to validate UITelemtry TBD
Processing TBD TBD TBD
Tooling TBD TBD TBD

Probe / Event dependancies and timeline

Name of probe design and review Use cases / questions list of events & priorities for implementation who implements and owns the probe who owns analysis
Activity Stream Events design use cases event list implement and own analysis owner
UItelemetry Events design use cases event list implement and own analysis owner
Search events design use cases event list implement and own analysis owner
Engagement measures events design use cases event list implement and own analysis owner
Test pilot events design use cases event list implement and own analysis owner
Mobile Telemetry design use cases event list implement and own analysis owner