Event Telemetry status report Sept 1, 2016
Overall Project Health
Last week: Green
This week: Yellow
Exec Summary
- Project enters yellow due to some uncertainty about dependencies.
- Need to understand event measurements in Activity Stream can be measured via the Event Telemetry approach
- Feedback required from UX
- continue work on understanding event registry
Risks/Issues
Description of Risks/Issues | State | Owner | Plan to Resolve/Mitigation | Target Date |
---|---|---|---|---|
Get sign off on proposal | In process | Georg | sign offs required from TestPilot (Will Clouser), Ilana, RobFromBRC, John Dorlus, | ASAP |
Notify Org post signoff | TBD | Thomas/Georg | Notify FX-Team, UITour stakholders, Jared, Mike Connoly | TBD |
Assess what event measurements in Activity Stream can be measured via the Event Telemetry approach | in flight | Ilana | Investigate | ASAP |
Escalate request for UX feedback to Product and Data leadership | In process | Katie | Escalation | TBD |
event registry integration in add-ons | In process | Georg | seek consensus | ASAP |
Accomplished for Last Period
- Kick off meeting
- RACI established
- investigations/Action items were generated
Planned for Next Period
- Assess what event measurements in Activity Stream can be measured via the Event Telemetry approach
- Escalate request for UX feedback to Product and Data leadership
- Talk to glind, mattg, mark banner about the event registry integration in add-ons
Proposed development stages and status
Stage | State | description | Target Date |
---|---|---|---|
Proposal creation | Done | accepted | August 1, 2016 |
Kick off | Done | RACI + develpoment stages | August 14, 2016 |
Development to allow test pilot to begin using and submitting | TBD | ingestion, storage, make available for analysis | TBD |
QA Validation | TBD | Test to validate UITelemtry | TBD |
Processing | TBD | TBD | TBD |
Tooling | TBD | TBD | TBD |