Kilimanjaro/2012-04-23
From MozillaWiki
Recent Progress
- Meeting last Thurs to run through Claire user scenario.
- Sheila posted to dev planning about process for tracking/tagging bugs.
- Next actions for people to add in bug links for dev platform items.
- Lawrence added meta bugs/links for all the high level use cases/requirements.
- Still not many bugs logged/nominated.
- Need a plan to aggressively drive towards defining all the work.
Plan
- Sheila/Lawrence to log all top level P1 meta bugs.
- Asa to post to the list prior to Tuesday dev meeting giving people until the end of the week to add sub bugs or engage with product to clarify requirements.
- Set a goal to have first level defined by the end of the week.
- Triage session post dev meeting to work through noms. Define second triage session, maybe Thurs.