Start of project
- Name each of the following:
- Project sponsor - William Reynolds
- Main IT contact - TBD
- Metrics contact - TBD
- Main WebDev contact - Mike Morgan
- Main QA contact - Raymond Etornam
- Main Security contact - TBD
- Main third party contact (if developed externally) - Craig Cook
- Final application owner/maintainer - William Reynolds
- Project sponsor - William Reynolds
- Outline the following:
- Overall goal of the project - Implement 5 new pages for Student Reps on mozilla.org
- Any pre-requisites needed (technology, server capacity, staffing, monitoring, response time, etc)
- Initial timeline
- External dependencies - None
- Dev environment specs
- Does this project use any plugins or proprietary technology?
- Overall goal of the project - Implement 5 new pages for Student Reps on mozilla.org
Staging Signoff
In order to get an app into staging, the following should be completed:
- Code committed to Mozilla source control and tagged
- Initial architecture review by IT and WebDev
- Plugin/tech review by Evangelism
- Security review must be in-process
- Site must be password protected
- Review timeline to go live
- Review any production requirements so IT can order any new hardware needed
Production Signoff/Launch
- Final WebDev signoff
- Final IT signoff
- Final QA signoff
- Final Security signoff
- Final Metrics signoff
- Operations documents filled for support & any training complete
- Monitors in place