Firefox 39 Post-mortem
Special section about 38.0.6
(sylvestre) * funnelcake => is it still a thing? (similar to partner repack)
- testing of funnelcake
- automation on search test
- is there a list of these?
- we should have a list of the partner somewhere
- mike connor
- we should have a list of the partner somewhere
39.0
- (bhearsum) EMEFree should user mozilla- prefix (is there a bug?). Shipped in 38
- If we rename the channel, do we need a special mar? https://bugzilla.mozilla.org/show_bug.cgi?id=1183734
- (bhearsum) win64 builds completely missed as part of 39.0
- did we have a tracked bug? https://bugzilla.mozilla.org/show_bug.cgi?id=1180792
- will do for 40 + update the download page to propose this build to adv users
- maybe communication on 42 or 43 - Javaun is the guy in charge
- will do for 40 + update the download page to propose this build to adv users
- did we have a tracked bug? https://bugzilla.mozilla.org/show_bug.cgi?id=1180792
- (UA - Robert) Malware Crash Post-Mortem: https://docs.google.com/document/d/1d-m-CmumtDSlNNMRQiWf2IOC9_zgtFjnmblXJAfI3KM/edit#
- If we want a faster response we should foster better relationships with AV companies to get files early and without having to rely on users
- (Alternatively we could have better file collection utils built-in, but that'd be a lot of work / potential new attack vector / etc)
- relman has some contacts with AV
- UA needs to work on making their surveys look more official
- (KaiRo) As inconvenient the scrambling around the adware startup crash was, and as unsatisfactory overall the "solution" might feel, this story was a good example of our RC process at work, thanks for everyone involved to make it work!
- especially during the Workweek
- however, we would have to improve the internal communication
- (lmandel) We shipped 39.0 two days late. Might be the first time that we've found a critical issue and fixed it before release.
- (lmandel) We did a better job of limiting feature uplifts in this cycle (congrat liz)
- suggested tiles
- (lmandel) Whistler made it difficult to shutdown the release due to the late issue that was found. It would probably be preferable to have the all-hands in the middle of the cycle rather than at the beginning or end.
- but it will be the same in Orlando
- (rituk) Short beta cycle - 5 weeks instead of 6 weeks. Kudos! Does that mean we can ship every 5 weeks now?!
- This might be because 39 did not include several features. Another release would have had an impact due to a shorter cycle.