Firefox Activity Stream Program - Cross-Platform Status Report - Jan-12-2017
Overall Project Health
On track, issues well managed Some risks, unknowns without clear mitigations Blocked on deliverables, needs decision, escalation required
Platform/Area | Version | Health | Notes |
---|---|---|---|
Desktop | TBC | Yellow status due to the fact that final MVP breakdown work and schedule is still pending. Shield study is complete and report of findings will be distributed soon. Work week next week (Jan 16-20). | |
Android | FF54 | Currently in sprint 1.13 (ending Jan 22). MVP feature set on track for FF54. | |
iOS | V8.0 | Currently in sprint 1.13 (ending Jan 22) and V7.0 development period is in progress. MVP feature set on track for V8.0. |
Exec Summary/Hot Topics
General
- Engineering breakdown of MVP user stories is complete for both mobile platforms, and forecasting completed.
- Desktop work week happening Jan 16-20 to complete MVP breakdown, discuss any changes necessary based on finding from Shield study, finalize forecasting, define work required for TestPilot graduation, and also define Q1 OKRs.
Desktop
- Current Sprint 'Quttinirpaaq'
- Planning to complete MVP breakdown work and MVP delivery forecast in January (16-20).
- Discussions have begun on how to 'graduate' AS code to the trains, vs the current add-on. More in depth discussion planned for January work week.
- Shield study completed. Summary reported of findings will be distributed soon. Feature changes based on findings will be defined during the work week next week.
Android
- Current Sprint 1.13
- Breakdown and forecasting complete.
- Continuing on with remaining MVP feature development. MVP Backlog can be found here.
- On track for FF54
iOS
- Current Sprint 1.13
- Breakdown and forecasting complete.
- Continuing on with remaining MVP feature development. MVP Backlog can be found here.
- On track for V8.0
Risks & Issues
Description of Risk/Issue | Affected Platform(s) | State | Owner | Version | Plan to Resolve/Mitigation | Target Date |
---|---|---|---|---|---|---|
Team work capacities & therefore MVP delivery date unknown | All | Open | Jenn | TBD | Closed for mobile, but still open for Desktop. Will be addressed and resolved during January work week. | Jan 20th |
Development Status
On track, issues well managed Some risks, unknowns without clear mitigations Blocked on deliverables, needs decision, escalation required
For more details please visit the Activity Stream Trello Board
MVP Feature Development
- This section to be populated upon completion of MVP Definition and Breakdown. In the meantime please see the following for development state details:
- Desktop on GitHub
- Mobile Sprint Planning - work still to complete for current sprint
- Mobile Performance - work completed to date
Feature Description | Platform(s) | Meta Bug | Health | Status |
---|---|---|---|---|