Firefox Activity Stream Program - Cross-Platform Status Report - Oct-11-2016
Overall Project Health
On track, issues well managed Some risks, unknowns without clear mitigations Blocked on deliverables, needs decision, escalation required
Platform/Area | Version | Health | Notes |
---|---|---|---|
Desktop | Add-On | 'La Mauricie' sprint kicked off, with end date of Oct 23rd. Yellow status due to the fact that final MVP definition is still pending, and final delivery date for the add-on is not confirmed. | |
Android | FF52 | Currently in sprint 1.6 (ending Oct 16) with work landing in FF52. Currently not confirmed if 52 is the delivery vehicle as final MVP definition is still pending (hence Yellow status). | |
iOS | V6.0 | Currently in sprint 1.6 (ending Oct 16). Release date for the V6.0 delivery vehicle is not yet confirmed as final MVP definition is still pending (hence Yellow status). |
Exec Summary/Hot Topics
General
- Team work week took place Sept 27-29 in Toronto. The team covered many topics from MVP definition, Cross-functional feature brainstorming, process improvements and OKRs for Q4.
- Product is currently working on finalizing/solidifying the MVP definition for all platforms.
- Jennifer Chaulk transitioning in as EPM for Activity Stream across all platforms
Desktop
- Current Sprint 'La Mauricie'
- Priorities for this sprint are Performance & Shield Study deployment
Android
- Current Sprint 1.6
- Priorities - new tab/home panel, highlights
- Team capacity calculations to begin after this sprint, for future planning & forecasting
iOS
- Current Sprint 1.6
- Priorities - new tab/home panel, highlights, Focus updates
- Team capacity calculations to begin after this sprint, for future planning & forecasting
Risks & Issues
Description of Risk/Issue | Affected Platform(s) | State | Owner | Version | Plan to Resolve/Mitigation | Target Date |
---|---|---|---|---|---|---|
Final MVP definition still to be solidified | All | Open | Barbara/Nick | TBD | Product is currently working on finalizing MVP definitions for all platforms, based on discussions/outcomes from the work week last month | Oct 17th |
Team work capacities & therefore MVP delivery date unknown | All | Open | Jenn | TBD | Team is investigating use of Monte Carlo analysis/simulation used by other teams to calculate team capacity, which will also support development of MVP delivery forecast. Dependent on Product finalizing the MVP definition. | |
Development Status
On track, issues well managed Some risks, unknowns without clear mitigations Blocked on deliverables, needs decision, escalation required
For more details please visit the Activity Stream Trello Board
MVP Feature Development
- This section to be populated upon completion of MVP Definition. In the meantime please see the following for development state details:
- Desktop on GitHub
- Mobile Sprint Planning - work still to complete for current sprint
- Mobile Performance - work completed to date
Feature Description | Platform(s) | Meta Bug | Health | Status |
---|---|---|---|---|
Important Links/References
- Desktop on GitHub
- Mobile Sprint Planning - work still to complete for current sprint
- Mobile Performance - work completed to date