Vaani
|
Validation (Aaron/Sandip)
|
On Target
|
- Engineers are focusing on Prototyping as 1st showcase which targeted by this week
- End-to-end use case - "As a user, I would like control my floor lamp with voice"
- Speech to Text
- Text to Speech
- Triggering Word ("hey Vaani, turn on (off) the floor lamp")
- IOT integration (OpenHAB )
- Vaani MVP Architecture - goo.gl/zaxdXz
- Discussed with Metrics group to make dashboard powered by Telemetry
- Guiding community to explore OpenHab and Pocketsphinx on RPi using One and Done
- Program Milestone tracking table - milestone, schedule and dependencies
|
Project Link
|
Validation Stage (Mars/Preeti)
|
On Target
|
- End-to-end tests running!
- Walking Skeleton stories 1 & 2 functionally complete, test framework in progress
- Walking Skeleton stories 3 & 4 in progress
- Demos of Webpush, OpenZWave, Account creation pages, IP Camera, Chromecast
- Innovation board progress update this week
- Market research starting next week
- London demo planning started
- Participation ideas call this week
- Work week next week in MTV
- Full list of weekly updates
|
Smart TV for 2.6
|
Josh
|
On Target
|
|
Smart TV Next Gen
|
Validation (Joe/Josh)
|
On Target
|
- Working on use cases that enhances the user's engagement experience with the TV by offering better remote control, content discovery, personalization, multi-user experiences.
- In parallel, we are exploring to work with an external creative agency to help us either make our ideas better or create even better new ideas.
- Strategy Analytics research material:
|
WADI
|
Thomas/Bill
|
On Target
|
- General
- Partnerships
- Major Social network provider has rolled out Push notifications services to internal testing audience (~1000 users). Over the several weeks this is expected to incrementally increase upwards of 100m+ subscribed users.
- Engineering (no significant updates from last week)
- Word Press plugins for Push, Offline, and Add to Homescreen still on track for end of Q1 completion
- Crawler MVP on track for end of Q1.
|
Research
|
Lindsay
|
On Target
|
- We have kicked off the technical research with the team
- Current research includes, Zigby, Z wave, AWS ioT, Open WRT/DD-WRT, Johnny-Five, Google's Physical Web, Google Weave/Brillo, IBM Watson
- The team is starting their experiments and will have the next standup on Thursday to review progress
- Working on getting the user research contractors who should start 3/21
- email list ResearchTeamCD@mozilla.com and irc channel #ResearchTeam are ready to be joined if you would like to follow updates
- Wiki will be up this week for all 3 of the research avenues, technical, user and market
|
Project SmartHome
|
Maria/Liz
|
On Target
|
- Smart home research plan already drafted (it will take around 6 weeks)
- It will identify and test the user hypotheses before we start building
- It's divided in 3 phases
- For the time being engineering team is focused on exploring the current technology
- We are planning to have a working week from 4th to 8th April in Portland, where we can start working on the implementation of the solution
|
Project Sensor Web
|
Cindy/Wesley
|
On Target
|
- Program wiki updated https://wiki.mozilla.org/SensorWeb
- Upcoming milestones
- 3/28 demo-able end user scenario with web pages. (Dummy PM2.5 data from the pizza box R-Pi2 or hardcoded)
- 4/18 P1 bugs (namely the MVP) complete.
|
Porting
|
Nicole/David/Peter
|
On Target
|
- Smart TV
- Brian in communication with TPE about possible opportunities to have community involvement.
- Fairphone 2
- Juan helping folks working on Fairphone 2 who still want to host builds
- Rpi2
- same state as last week
- waiting for flash script to be reviewed
|
FlyWeb
|
Nicole/Dylan
|
On Target
|
- Roadmap into Q2 completed
- Landed http server
- working on JS implementation for advertising
- Work week in TOR April 4-8 for UI/UX Ideation
|
Firefox OS Smartphone Sunset
Smartphone Transition Wiki
Smartphone Code Transition Wiki
Smartphone Commercial Transition Wiki
B2G OS Transition to Community Wiki
|
Smartphone Commercial Sunset (David)
|
On Target
|
Main updates this week:
- Working with Product Marketing team to update/review the pages/sites related to Firefox OS (sites like blog.mozilla.org, branding site, etc).
- Legal to send some notices to partners this week
- Some summarized info (skipping partner-related info and legal info) is being published in a wiki). This is work in progress.
|
Code Transition (Julie)
|
On Target
|
- Engineering team formed and assignments made. Work has begun. Need to develop a schedule with milestones.
- Currently dealing with a lot of breakage and working on fixes. This was expected.
- Team is meeting weekly at Taipei and Europe friendly times.
|
Foxfooding (Jean)
|
On Target
|
- Last Foxfooding OTA update released March 2 to users. This OTA build has foxfooding flag for data collection turned off
- Jean and Vik are deleting Community Foxfood users who "Opt-Out" of foxfooding program from tracking list as required by Legal
|
Transition to Volunteer Community (George)
|
On Target
|
- Kick-off meeting was held March 10th to form a team of Mozilla staff and volunteer contributors to develop a plan to transition b2g OS to the volunteer community. About 40 people attended. Check minutes in this Etherpad.
- Working groups were formed to identify next steps
|
Participation Update
|
David P
|
On Target
|
- Participation team is already working with the EPMs and PMs of each of the trains that have passed Gate 0 to explore and identify contribution opportunities for the community (specific measurable tasks to be performed by the community)
- Participation Hub will be redesigned to be focused on CD activities (work in progress, ETA end of April)
- Kick-off meeting for B2G OS was held last Thursday
|
Metrics for CD
|
Maria
|
On Target
|
- CD crash ping format already drafted
- Team is working in designing/creating Metrics Library/ies architecture that trains as Link and Vanni could use
- It’s based on David Teller’s Metrics Rust library but needs to be adapted and include a new Controler library
- Also for projects based in Java technologies (e.g vaani) we are developing a component that let them invoke the Rust native library via Java Native Access (JNA)
- Tracking the work in Trello the current tasks right now, during this week we should set the deliverables and milestones for H1
|
Other Announcements
|
David B
|
--
|
- Do Monkey - Brainstorm coming up. Overview today at research and strategy meeting 12:30 Pacific Time
- Marketplace - going dormant for phones 2 weeks. Working on next gen requirements for TV.
|