Weekly Status
9/19/08
- Weave server prototype is implemented
- Weave UE on Fennec is spec'ed out; remaining items are one-time tasks such as registration, login, preferences.
- Some progress on additional resources; still a yellow flag
9/12/08
- Weave server continued progress on implementation; on target
- Fennec team developing UE for integrating Weave features
- Additional resources to help with Weave on Fennec still pending
9/5/08
- Discussed Weave support feature requirements with Fennec team
- Preliminary plan with Milestones posted at 0.3 Release
- Prototyping new Weave server & API needed before other components can be built
Issues & Actions
Id | Issue | Owner | Status |
1 | Resources to deliver Weave 0.3 not finalized; waiting on task scoping. Plan not final. | nkishore | Finish task scoping and finalize resource plan |
2 | User experience for Fennec Weave extension is unscheduled currently | Fennec | Fennec team to determine UE |
3 | Need a reasonable solution to clean up data on phone if lost/stolen | Dan Mills | Open |
4 | Given limited local cache on device resolve degree to which data must be compressed. This needs testing to determine the best approach. | Dan | Open |
5 | Method of notifications in Fennec for reporting Weave alerts, warnings, logs, etc. | Stuart | Open |