Meeting Info
Teleconference: room 300
Mountain View: Dancing Baby (3rd floor)
Socorro Release Tracker
Socorro Bug Tracker
2.5.1
- bugs
- Ready to push today?
2.5.2
- bugs
- Freeze today, push next week.
ElasticSearch
- We have a plan
- Goal: in prod by March 28 (or as soon after as humanly possible)
Other issues
- Staging in PHX is ready! Let's stage 2.5.2 there.
- Want to rotate release management: next in line is Adrian (wait for ES to be done?)
- Q2 draft/high level goals. So far I have:
- [PARTIAL CARRYOVER] New reports for CrashKill group
- Leverage ES to give better insight into crash reports (ie start on the 50 dependent bugs)
- Modernize front end code (ie start on rewrite, finish data access -> middleware)
- Automate remaining manual infrastucture (cron job management, db updates, etc)