Betafarm/Weekly-Status-Reports/2012-03-27

From MozillaWiki
Jump to: navigation, search
Summary
DOC VERSION: 1.0 STATUS REPORT AS OF: March 27 2012
AUTHOR: Benjamin Sternthal
TPM: Benjamin Sternthal
PROJECT SPONSOR: David Ascher
PROJECT WIKI: Betafarm
Status
1. STATUS
Status Item On Track Caution Crisis N/A Comment
OVERALL STATUS X
Schedule X
Scope X
Budget X
Schedule & Budget
2. SCHEDULE
Start Date Completion Date
Original Current Original Current
Jan 17 Jan 17 March 30 April 9
3. BUDGET
Original Current
Cost Of Work
Performed
Estimated
Actual Cost
Variance
at
Completion
N/A N/A N/A N/A
Recent Accomplishments
4. RECENT ACCOMPLISHMENTS
  • Blog issues resolved
  • Coding continues
Upcoming Tasks
5. UPCOMING TASKS
Task Owner Due Date Bugzilla Comments
Launch Plan BB/PM/BS 3/23 --- In progress
Blog Import / Cleanup BS/Havi 3/29 --- Import complete
Major Issues
6. MAJOR ISSUES, CONCERNS & IMPACTS (* = new)
Issue Description Owner Priority Date Due Bugzilla Status
--
Project Milestones
7. PROJECT MILESTONES
Issue Owner Target
Completion
Date
Revised
Completion
Date
Actual
Completion
Date
Bugzilla Status
WebDev
  Release 1 Ready To Test PM/Jfong 3/28
  Release 1 Live PM/Jfong 4/9
Content
   Blog Import PM/HH 3/16 3/27
   Blog Cleanup HH 3/19 - 3/23 3/27- 3/30
Privacy
   Data Safety Review AH 3/15 3/25 728334 In Progress
   Privacy/Legal Review Jishnu 3/19 - 3/23 3/19 Complete
QA
   QA Review RB 3/28 - 4/3 728464
Security
   Security Review MG 3/28 - 3/30 718891
IT
   Setup Dev BB 3/7 733143 Complete
   Setup Staging BB 3/9 735773 Complete
   Production Plan BB/BS/PM 3/23 3/27