Summary
DOC VERSION: 1.0 STATUS REPORT AS OF: Feb 28 2012
AUTHOR: Benjamin Sternthal
TPM: Benjamin Sternthal
PROJECT SPONSOR: David Ascher
PROJECT WIKI: Betafarm
Status
1. STATUS
Status Item On Track Caution Crisis N/A Comment
OVERALL STATUS X
Schedule X
Scope X
Budget X
Schedule & Budget
2. SCHEDULE
Start Date Completion Date
Original Current Original Current
Jan 17 Jan 17 March 30 N/A
3. BUDGET
Original Current
Cost Of Work
Performed
Estimated
Actual Cost
Variance
at
Completion
N/A N/A N/A N/A
Recent Accomplishments
4. RECENT ACCOMPLISHMENTS
  • Branding issue decided.. going with mozillalabs.com
  • QA & Security Contacts Assigned & Looped In
  • Milestones stubbed out
Upcoming Tasks
5. UPCOMING TASKS
Task Owner Due Date Bugzilla Comments
Define Scope Q1 Release DA/BS 2012-02-20 --- Complete
Create IT Bugs/Dev/Stage/Figure Out Production BS /PM 2012-02-30 --- In Progress
Schedule Sign Off By Teams BS/Teams 2012-02-30 --- Complete
Major Issues
6. MAJOR ISSUES, CONCERNS & IMPACTS (* = new)
Issue Description Owner Priority Date Due Bugzilla Status
HP Design DA High 2012-03-07 728410
Decide on Branding & Domain Name DA High 2012-03-01 -- Complete
Project Milestones
7. PROJECT MILESTONES
Issue Owner Target
Completion
Date
Revised
Completion
Date
Actual
Completion
Date
Bugzilla Status
WebDev
  Release 1 Ready To Test PM/Tofu 3/16
  Release 1 Live PM/Tofu 3/30
Content
   Content Import PM/HH 3/16
   Content Entry HH 3/19 - 3/23
Privacy
   Privacy Review AH 3/19 - 3/23 728334
QA
   QA Review RB 3/19 - 3/23 728464
Security
   Security Review MG 3/26 - 3/28 718891
IT
   BB