Betafarm/Weekly-Status-Reports/2012-02-28
From MozillaWiki
< Betafarm
Contents
Summary
DOC VERSION: 1.0 | STATUS REPORT AS OF: Feb 28 2012 |
AUTHOR: Benjamin Sternthal |
TPM: Benjamin Sternthal |
PROJECT SPONSOR: David Ascher |
PROJECT WIKI: Betafarm |
Status
1. STATUS | |||||
Status Item | On Track | Caution | Crisis | N/A | Comment |
OVERALL STATUS | X | ||||
Schedule | X | ||||
Scope | X | ||||
Budget | X |
Schedule & Budget
2. SCHEDULE | |||
Start Date | Completion Date | ||
Original | Current | Original | Current |
Jan 17 | Jan 17 | March 30 | N/A |
3. BUDGET | |||
Original | Current Cost Of Work Performed |
Estimated Actual Cost |
Variance at Completion |
N/A | N/A | N/A | N/A |
Recent Accomplishments
4. RECENT ACCOMPLISHMENTS |
|
Upcoming Tasks
5. UPCOMING TASKS | ||||
Task | Owner | Due Date | Bugzilla | Comments |
Define Scope Q1 Release | DA/BS | 2012-02-20 | --- | Complete |
Create IT Bugs/Dev/Stage/Figure Out Production | BS /PM | 2012-02-30 | --- | In Progress |
Schedule Sign Off By Teams | BS/Teams | 2012-02-30 | --- | Complete |
Major Issues
6. MAJOR ISSUES, CONCERNS & IMPACTS (* = new) | |||||||
Issue Description | Owner | Priority | Date Due | Bugzilla | Status | ||
HP Design | DA | High | 2012-03-07 | 728410 | |||
Decide on Branding & Domain Name | DA | High | 2012-03-01 | -- | Complete |
Project Milestones
7. PROJECT MILESTONES | |||||||
Issue | Owner | Target Completion Date |
Revised Completion Date |
Actual Completion Date |
Bugzilla | Status | |
WebDev | |||||||
Release 1 Ready To Test | PM/Tofu | 3/16 | |||||
Release 1 Live | PM/Tofu | 3/30 | |||||
Content | |||||||
Content Import | PM/HH | 3/16 | |||||
Content Entry | HH | 3/19 - 3/23 | |||||
Privacy | |||||||
Privacy Review | AH | 3/19 - 3/23 | 728334 | ||||
QA | |||||||
QA Review | RB | 3/19 - 3/23 | 728464 | ||||
Security | |||||||
Security Review | MG | 3/26 - 3/28 | 718891 | ||||
IT | |||||||
BB |