Auto-tools/Projects/Foo
Overview
Detail your project's purpose:
Project Foo is a project to demonstrate this template. It is going to enable us to build tools at the speed of light while remaining permanently on vacation on a tropical island. Except Jhammel, who hates tropical islands and will be vacationing in Alaska. ;)
Deadline/Deliverables
List Deadlines and Deliverables:
If it's ongoing and has no deadline: Project Foo has no deadline, but we do want to get foo v0.1 released by end of Q2.
If it has a deadline: Foo must be completed by June 15 so we can be on vacation by June 20.
ATeam
Who's working on this
- Ctalbert
Dependencies
If you need machines, if you need another team to do something, call that out
- We need 4 battalions of armed robots to run the automation.
- Releng will have to deploy said armed robots.
Major Tasks
Breakdown Major Tasks and estimate how long they will take
- Design the FooManChu Subsystem 40hrs
- Implement the FooManChu Subsystem for Logging 8hrs
- Implement the FoomanBaz Automatomaton 32hrs
- Find/Fix Bugs 40hrs
- Release 16hrs
Of course these are all estimates, but try to be as accurate as you can and take into account however much parallelization you can get among your team.
Notes
Free form notes
Go CRAZY