SFx redesign timeline
From MozillaWiki
QA Test Plan
December 2008
- Dec. 5: Mary to hand off final files (done)
- Dec. 31: Neil to splice PSDs and create CSS/HTML (moved to Jan)
January 2009
Redesign:
- Jan. 15th: Neil to splice PSDs and create CSS/HTML (Now: Jan. 23)
- Jan. 26th: CSS/HTML implemented in SFX codebase/site staged (Now. Jan. 30)
- Jan. 28th: Marketing to provide feedback
- Jan. 30th: Alex to complete P1 admin needs for new SFx
Drupal Migration:
- Jan. 9th:
- Alex to file a bug to get a staging server up
- Jan. 16th:
- Mary, Paul and team to resolve Varbinary issue
- Alex to get staging server set up (is this an IT issue?)
- Jan. 19th: Get Sfx database copied over (is this still needed?)
February 2009
Redesign:
- Feb. 4th:
- Site iterations complete
- QA kicks off
Drupal Migration:
- Feb. 9th: Finish new theme
March 2009
Redesign
- March 4nd: New design live
Drupal 6 Migration:
- March 5th: Site QA kicks off for Drupal 6 migration
- March 31st: New Drupal 6-based site live.